隧道初期支护承包合同
篇一:下宅隧道初期支护施工方案(首件)
1、编制依据......................................................................................................................3
1.1编制依据..............................................................................................3
1.2适用范围..............................................................................................32工程概况.........................................................................................................................3
2.1工程概况..............................................................................................3
2.2工期计划..............................................................................................6
2.3施工场地布置.......................................................................................6
2.4主要技术手段.......................................................................................7
2.5主要工程数量.......................................................................................8
2.6不利条件..............................................................................................8
2.7有利条件..............................................................................................8
5、施工方案和方法........................................................................................................12
5.1施工前准备.........................................................................................12
5.2施工工艺............................................................................................12
6、质量保证措施............................................................................................................28
6.1质量保证体系.....................................................................................28
6.2管理方针与质量目标..........................................................................32
6.3质量保证措施....................................................................................32
七、工期保证措施..........................................................................................................40
7.1工期保证管理体系..............................................................................40
7.2为了确保工期,特制定以下保证措施.................................................40
8、安全保证体系及保证措施.......................................................................................41
8.1安全目标............................................................................................41
8.2安全生产管理组织机构.......................................................................41
8.3安全生产管理体系..............................................................................45
8.4安全生产管理保证措施.......................................................................46
8.5现场安全施工措施..............................................................................48
9、不利季节施工保证措施...........................................................................................53
9.1冬期施工措施.....................................................................................53
9.2雨期施工措施.....................................................................................54
9.3夜间施工措施.....................................................................................54
10、风险预测与防范、事故应急预案........................................................................55
10.1风险分析及防范措施........................................................................55
10.2突发事故应急预案............................................................................56
11、环境保护体系和保证措施.....................................................................................60
11.1环境保护目标...................................................................................60
11.2环境保护的保证组织体系.................................................................61
11.3环保的技术措施................................................................................61
12、文明施工措施.........................................................................................................66
12.1文明施工保证措施............................................................................66
下宅隧道初期支护施工方案(首件)
1、编制依据
1.1编制依据
1.1.1贵州省沿河至榕江高速公路沿河至德江段施工招标文件、图纸、补遗书等相关资料;
1.1.2现行有效的国家标准和交通部颁发的公路施工技术规范、规程、指南;
1.1.3贵州省对于高速公路建设的相关法律和要求;
1.1.4工程承包合同、协议、纪要等有效合同文件;
1.1.5建设单位明确的施工日期、质量和环境保护要求及关键工程控制要点;
1.1.6现场踏勘获取的资料,包括施工场地和周边环境条件,水电路临时租地等情况,水文地质气象,交通、机械等;
1.1.7人力资源、材料、设备和经济方面的实际情况;
1.1.8本公司拥有的科技成果、工法成果、机械设备、技术水平及多年积累的施工经验。
1.2适用范围
本方案适用范围为:沿德高速公路第5合同段下宅隧道初期支护施工工程。本方案内容主要侧重于对隧道初期支护施工要点的保证,未涉及的各种施工技术要求,严格按《公路隧道施工技术规范》(JTGF60-20XX)执行。
2工程概况
2.1工程概况
下宅隧道为一座分离式长隧道,左洞zK43+220—zK44+228,长1008m,右洞YK43+225—YK44+250,长1015m,左洞iii级围岩500m,Ⅳ级围岩394
米,Ⅴ级围岩94米;右洞iii级围岩522m,Ⅳ级围岩381米,Ⅴ级围岩92米。下宅隧道设2处人行横道,1#横洞洞长22.11m,所处围岩类别为Ⅲ级;2#横洞洞长22m,所处围岩类别为Ⅲ级;一处车行横道,横通道长度25.36m。左、右线进口端设5m明洞(端墙式),出口端设15m明洞(削竹式)单洞净空(宽X高):10.25×5.0m。
2.1.1自然条件
(1)地形、地貌
场区地处贵州东北部,大娄山脉与武陵山脉接壤部位。位于沿河县境内,隧横穿山林,进口位于陡坡地带,出口位于缓坡地带。场区海拔771.3~1082.9m,相对高差311.6m;隧道通过地面高程822.4m-954.3m之间,相对高差131.9m,隧道区基岩大部裸露。地貌类型属溶蚀型低山地貌。进口段植被不发育,出口段植被不发育,多为耕地。隧道出口左侧为G326国道,交通方便。
(2)水文、气候
场区属长江流域之乌江水系。隧道出口有一溪流通过,流量约2l/s,地表水主要为大气降水补给,受季节影响大。
区域内气候宜人,夏无酷暑,冬无严寒,四季不甚分明,气候温和,阳光充足,雨量充沛,属典型的中亚热带季风湿润气候。全年平均气温在13℃~17℃之间,无霜期达295天,最冷月(1月)平均气温5℃左右,最热月(7月)平均气温23℃左右。年降雨量900~1500mm,年均降雨量1180mm,一般五月至七月间和十月份雨量较多。全年日照时数为1115.4小时。气候特点是热量丰富、雨量充沛、水热同季。